Summer Kitchen Renovation Part2: Water & Electricity

When I started healing from my strained back we invited the excavator back to do the work we halted a couple of weeks earlier. I offered guidance, Iulia did the work!

We started working on a water line. There was already a second pipe (the first being the one that feeds into the house) coming out of our water infrastructure. We decided to extend it and attempt to bring it into the summer kitchen (I felt this was the best time to try this, before burying the electric power cable). We excavated parallel to the existing water line to avoid injuring the working pipe:

Iulia promptly continued with some manual digging around the existing pipe, to loosen the soil around it enough to bury it in full depth (~80cm deep):

While Iulia was doing that Florin created the channel from right up against the house until we had a full path:

We then patched the existing pipe to a new segment, placed it in the ground and very quickly the excavation was closed off (except for the part near the structure where we would need to manually dig to get the pipe inside):

We then moved on to burying a new main electric cable (more on that project as it unfolds). This is a fairly massive armored cable (4 lines of 16sqmm aluminum wires). We started by excavating a channel between the house and summer kitchen (which will be connected to the house). It is shaped as two diagonals because of limited space for the excavator to maneuver):

Then we began to dig the line out and away from the house:

… and around the summer kitchen. The cable is buried ~50cm deep, so it crosses over the water pipe:

We then moved our attention to the other end of this cable, to where a new electric post would be installed. We first transplanted a plant that was occupying the location of the new post:

We then continued the ditch to the post location:

Then we came to the hole for the post itself:

then the cable went in:

… and once again everything was quickly buried again:

This kind of infrastructure work doesn’t leave much of a trace … the materials and work simply get swallowed and converted into potential value!

… this was completed ~3 weeks ago … to be continued 🙂

Categories
Cob Construction

Summer Kitchen Renovation Part1: Destruction

For the past few months Iulia has been clearing out the summer kitchen in preparation for renovation. We haven’t started because I’ve been reluctant to get into this project. During this period of my reluctance we did get more clear about the general plans for the renovation. We also got a set of 4 used windows that helped us make some design choices.

Then on the weekend of the July 20th Alin came to visit with us again. I was still reluctant to start, so on the first day we cut some firewood together. His presence and ability to help with physical work did bring us to a point of “critical energy”. I walked around the cellar and found clarity about where to start. The next day we started.

The small space in the summer kitchen had a baking stove built into the rear wall. We started by taking it apart. This image was taken after the exterior (sticking out the back of the structure) part of the dome was disassembled. This the inner half of the oven dome with the metal door opened and looking into the space.

This is after Alin went inside and collapsed the chimney and other inner parts:

The base of the oven was filled with dirt, stones, broken bricks … and plenty of broken glass:

We discovered three kinds of bricks: regular fired clay bricks, unfired (we are guessing home-made) cob-bricks and large flat slabs of fire-bricks (shamota) that created the baking base. We tried to organize materials for later to re-use. We had to set aside the materials that were mixed with glass (we tried sieving but small glass parts got through). We kept the whole & semi-whole clay bricks close to the opening with the intention of reusing them to rebuild it:

Behind the pile of cob-bricks in the above picture there is a similar pile of whole clay-fired-bricks and not far away accumulated a pile of broken bricks:

That was completed on our first day of work and on the next day we moved on to breaking down some cob-wall and converting the small window into a doorway between the small space and the main space of the summer kitchen.

Alin climbed up on the roof and started taking the wall apart from the top

… and (to my surprise) the rest came down fairly quickly (even though we did not have the right tools for the task!):

By the end of this day we had an opening all the way to the ground:

During the demolition we were getting nice chunks of cob. On the first day I put a few of them in a bucket of water to see if the cob could be re-activated … and it worked beautifully. So we created a cob-bath and loaded it up with what we considered to be re-usable cob materials. I was a bit naive about the size of the bath … it filled up very quickly. We soaked it all in water and let it sit and it has become beautiful, ready to use cob:

There is already a second larger pile that we are gradually dampening to bring it closer to work-readiness:

The next day was planned to be a work day with the excavator … but life happened … so we are on hold for a while … we hope to start moving again next week.